Letter To VIHA regarding Streetscape Progress

Dear Mr. Brendel and Mr. Khamsi,

I hope all is well.  In an effort to keep the Venetian Island’s HOA updated on the construction activities of the Venetian Islands Neighborhood Improvements Project, as well as work together to achieve optimum outreach results, please note that the contractor is scheduled to begin excavation for drainage installation on the southwest side (curve area/peak of island) of San Marino Island, the week of March 2, 2015 (next week).

As previously discussed in past meetings, we would greatly appreciate your assistance in keeping the residents informed.  During this process, it is important to inform residents that back door garbage collection service will not take place during the drainage phase.  Therefore, please advise them to place their garbage bins outside in front of their properties.  We will also distribute this information along with updated construction activity information through our weekly updates.

I thank you for your cooperation throughout the construction process, and look forward to working together.  Take care and have a great weekend!

 

Regards,

Quest Corporation of America, Inc.

Yaisel Gonzalez

Public Information Specialist

305.345.7269  |  o 866.662.6273  |  f 813.926.2962

Yaisel.Gonzalez@QCAusa.com  |  QCAusa.co

Venetian Islands Streetscape Update

BRIEF UPDATE ON STREETSCAPE

We would like to give residents a short update of what’s happening with our ‘somewhat neglected’ streetscape.

In a meeting with CIP yesterday, VIHA was given the following Agenda:

1. Storm Water Drainage will start in February/early March starting with San Marino and last approx. 2 months.

Dilido will start thereafter and last 3 months, once completed Rivo Alto will last 2 months.

2. As Rivo Alto will be last in this project, it was decided to give the Roads in Rivo Alto a temporary asphalt overlay.

It does not make any practical or economic sense for the other islands as they are being worked on.

3. The storm water drainage work will be done in segments of 300 feet in order to not disrupt the entire traffic to the islands.

There will be no disruption to mail delivery or sanitation pick-up, but changes are needed to guarantee access.

Lastly, please pay attention to instruction for parking your car, best it be in your driveway during this period. Access to your property will always be guaranteed.

 

THE ENTIRE PROJECT WILL LAST 14 MONTHS, pump stations at the end of each island will be installed in-between

More detailed instruction to follow from CIP.

Venetian Islands Construction Schedule – Letter from Lanzo

Please, see below the status of the drainage installation and road restoration (should we get an Notice to Proceed, NTP, of January 5, 2015) according to the current schedule.  Please, note this list/breakdown only includes drainage installation, temporary road restoration, road restoration, and final lift of asphalt with the original contract production rates:

  • Drainage NTP for Lanzo (Jan 05, 2015)
  • Drianage Shop Drawings resubmittal (DiLido & Rivo Alto) – Pending
  • Delivery of Stormwater Structures – San Marino has a start date of 17-Dec-14 (according to this date, the structures should be on production by now; therefore, any dates here presented are subject to change.  As it is, the Precast Manufacturer is to shut down operations the last two weeks of 2014)
  • Deliver of Stormwater Pipe – A-2000, schedule says that the start date is 31-Oct-14 (this pipe should at least have been ordered by now)

o   North San Marino

  • Drainage installation from Jan 26 to Mar 03, 2015
  • Temporary Road Restoration from Jan 29 to Mar 04, 2015
  • Road Reconstruction from Feb 13 to June 04, 2015
  • Final Lift of Asphalt 19-Oct-15 to 23-Oct-15

o   South San Marino

  • Drainage installation from Jan 22 to Feb 27, 2015
  • Temporary Road Restoration from Jan 27 to Mar 02, 2015
  • Road Reconstruction from Mar 05 to June 04, 2015
  • Final Lift of Asphalt 19-Oct-15 to 23-Oct-15

o   North DiLido

  • Drainage Installation from Mar 12 to Jun 05, 2015
  • Temporary Road Restoration from Mar 20  to June 08, 2015
  • Road Reconstruction from April 28 to Oct 01, 2015
  • Final Lift of Asphalt 19-Oct-15 to 30-Oct-15

o   South DiLido

  • Drainage Installation from Mar 11 to June 03, 2015
  • Temporary Road Restoration from Mar 18 to June 04, 2015
  • Road Reconstruction from Apr 23 to Oct 05, 2015
  • Final Lift of Asphalt 20-Oct-15 to 02-Nov-15

o   North Rivo Alto

  • Drainage Instllation from Jun 17 to Aug 07, 2015
  • Temporary Road Restoration from June 26 to Aug 10, 2015
  • Road Reconstruction from Jul 17 to Oct 22, 2015
  • Final Lift of Asphalt 03-Nov-15 to 09-Nov-15

o   South Rivo Alto

  • Drainage Instllation from June 17 to Aug 31, 2015
  • Temporary Road Restoration from June 30 to Sep 01, 2015
  • Road Reconstruction from July 23 to Oct 22, 2015
  • Final Lift of Asphalt 03-Nov-15 to 09-Nov-15

 

www.lanzo.net