Please, see below the status of the drainage installation and road restoration (should we get an Notice to Proceed, NTP, of January 5, 2015) according to the current schedule. Please, note this list/breakdown only includes drainage installation, temporary road restoration, road restoration, and final lift of asphalt with the original contract production rates:
- Drainage NTP for Lanzo (Jan 05, 2015)
- Drianage Shop Drawings resubmittal (DiLido & Rivo Alto) – Pending
- Delivery of Stormwater Structures – San Marino has a start date of 17-Dec-14 (according to this date, the structures should be on production by now; therefore, any dates here presented are subject to change. As it is, the Precast Manufacturer is to shut down operations the last two weeks of 2014)
- Deliver of Stormwater Pipe – A-2000, schedule says that the start date is 31-Oct-14 (this pipe should at least have been ordered by now)
o North San Marino
- Drainage installation from Jan 26 to Mar 03, 2015
- Temporary Road Restoration from Jan 29 to Mar 04, 2015
- Road Reconstruction from Feb 13 to June 04, 2015
- Final Lift of Asphalt 19-Oct-15 to 23-Oct-15
o South San Marino
- Drainage installation from Jan 22 to Feb 27, 2015
- Temporary Road Restoration from Jan 27 to Mar 02, 2015
- Road Reconstruction from Mar 05 to June 04, 2015
- Final Lift of Asphalt 19-Oct-15 to 23-Oct-15
o North DiLido
- Drainage Installation from Mar 12 to Jun 05, 2015
- Temporary Road Restoration from Mar 20 to June 08, 2015
- Road Reconstruction from April 28 to Oct 01, 2015
- Final Lift of Asphalt 19-Oct-15 to 30-Oct-15
o South DiLido
- Drainage Installation from Mar 11 to June 03, 2015
- Temporary Road Restoration from Mar 18 to June 04, 2015
- Road Reconstruction from Apr 23 to Oct 05, 2015
- Final Lift of Asphalt 20-Oct-15 to 02-Nov-15
o North Rivo Alto
- Drainage Instllation from Jun 17 to Aug 07, 2015
- Temporary Road Restoration from June 26 to Aug 10, 2015
- Road Reconstruction from Jul 17 to Oct 22, 2015
- Final Lift of Asphalt 03-Nov-15 to 09-Nov-15
o South Rivo Alto
- Drainage Instllation from June 17 to Aug 31, 2015
- Temporary Road Restoration from June 30 to Sep 01, 2015
- Road Reconstruction from July 23 to Oct 22, 2015
- Final Lift of Asphalt 03-Nov-15 to 09-Nov-15