BRIEF UPDATE ON STREETSCAPE
We would like to give residents a short update of what’s happening with our ‘somewhat neglected’ streetscape.
In a meeting with CIP yesterday, VIHA was given the following Agenda:
1. Storm Water Drainage will start in February/early March starting with San Marino and last approx. 2 months.
Dilido will start thereafter and last 3 months, once completed Rivo Alto will last 2 months.
2. As Rivo Alto will be last in this project, it was decided to give the Roads in Rivo Alto a temporary asphalt overlay.
It does not make any practical or economic sense for the other islands as they are being worked on.
3. The storm water drainage work will be done in segments of 300 feet in order to not disrupt the entire traffic to the islands.
There will be no disruption to mail delivery or sanitation pick-up, but changes are needed to guarantee access.
Lastly, please pay attention to instruction for parking your car, best it be in your driveway during this period. Access to your property will always be guaranteed.
THE ENTIRE PROJECT WILL LAST 14 MONTHS, pump stations at the end of each island will be installed in-between
More detailed instruction to follow from CIP.